May,
June, July 2007 Trail Work at Tellico August 3, 2007
Information provided by Rob Theurer, SFWDA Tellico Representative
Our totals on trail work are as follows:
| Month | Labor |
Machine time |
Value |
| May 2007 | 39 hours |
104.5 hours |
$6,689.50 |
| June 2007 | 250.5 hours |
312.5 hours |
$14,005.50 |
| July 2007 | 409 hours |
586.5 hours |
$29,545.00 |
TOTAL |
698.5 hours |
1003.5 hours |
$50,240.00 |
During this time, we:
In addition there were another 179.5 hours of contractor machine time and over 450 man-hours of repairs and maintenance performed on SFWDA equipment in the field.